CWC Team Inspects Polavaram Project Works
The officials inspected the ongoing works on the diaphragm wall, buttress dam, Gap-1, upper and lower cofferdams, and the spillway.
Hyderabad | 14th June 2025
A Central Water Commission (CWC) team today visited the construction site of the Polavaram project.
The team comprised Water Commission Member Yogesh Paithankar, Chief Engineer H S Sengar and Polavaram Project Authority Chief Engineer Ramesh Kumar.
During their visit, the officials inspected the ongoing works on the diaphragm wall, buttress dam, Gap-1, upper and lower cofferdams, and the spillway.
Water Resources Department officials briefed the central team on the construction progress of the diaphragm wall and the buttress dam. The officials said that both the Central and State governments were working in close coordination on the project. The central team urged officials to expedite the works in line with the project timeline.
The inspection team was accompanied by Polavaram ENC K Narasimhamurthy; Executive Engineers D Srinivas and K Balakrishna; Deputy Engineers Anil Kumar, Sriram Patel and Mallikarjun; Assistant Executive Engineers Anil Kumar, Padma Kumar, Suresh, Arun and Kumaraswamy; and MEIL Polavaram Project GM Gangadhar, DGM Murali Pammi, Pandey and Venkatesh.
filed in: Andhra Pradesh, Water Projects, Polavaram, Polavaram Project, Godavari River, Godavari Water Project